Collect machine data without changing the PLC program
Those counts and downtime records contribute to production analysis. For a complete OEE calculation, combine FactoryVision’s counts and downtime records with planned production time, ideal cycle time, and separately recorded good-part counts.
FactoryVision runs in a Turkish door and furniture factory. Buying starts with an introductory call.
FactoryVision uses a fixed camera to observe the work area. There are no sensors to fit to the machine and no wiring into it.
The setup has three elements:
- **A fixed camera:** One camera per machine counts visible finished parts.
- **A printed scale marker:** The marker provides a real-world millimetre scale and helps the system detect camera movement.
- **A local computer:** The models run on a small computer in the factory, not in our cloud.
Teaching a cycle takes ten parts. The setup target is under an hour per station.
Which data does OEE need?
OEE, or Overall Equipment Effectiveness, multiplies three factors:
- **Availability:** run time divided by planned production time.
- **Performance:** actual output during run time compared with output at the ideal cycle time.
- **Quality:** good parts divided by total parts produced.
FactoryVision counts visible finished parts and tracks downtime. To calculate the factors, define the measurement period and combine the relevant production and downtime records with planned production time, ideal cycle time, and good-part counts from the appropriate records. Agree on which stoppages count against planned production time and apply that rule consistently. Define downtime categories and recording rules for your machines during the introductory process.
Read station status during the shift
FactoryVision compares finished work with the day’s target and shows one status light per station:
- **Green:** on track.
- **Yellow:** at risk.
- **Red:** behind.
The status gives the production team a view of progress. The team can use its knowledge of the process to investigate a delay and decide what to do.
Choose a suitable production process
FactoryVision is designed for countable, discrete parts that the camera can see. The system runs in a Turkish door and furniture factory. Continuous processes such as extrusion are outside it.
The camera needs a suitable view of the work. Discuss the parts, machine layout, and camera position during the introductory process.
FactoryVision counts parts and shows station status. It is not an ERP, MES, or SCADA system.
Explain the camera’s purpose to the team
Tell operators what the camera is intended to observe: finished parts and station activity for production tracking. Presenting cameras as worker monitoring creates resistance, so make the intended production use clear when introducing the system.
Sources and claims
| Claim | Source |
|---|---|
| One camera per machine; no sensors to fit or wiring into the machine | Supplied house-style sample |
| Printed marker provides a millimetre scale and detects camera movement | Supplied house-style sample |
| Teaching a cycle takes ten parts; setup target is under an hour per station | Supplied house-style sample |
| Models run on a small computer in the factory, not in FactoryVision’s cloud | Supplied house-style sample |
| Station status uses green, yellow, and red for on track, at risk, and behind | Supplied house-style sample |
| Scope includes visible, countable discrete parts; extrusion is outside scope | Supplied house-style sample |
| FactoryVision tracks downtime | Founder facts |
| OEE factors and calculation inputs | OEE calculation guide |
| Worker-monitoring framing can create operator resistance | Demand synthesis |
| Working product, use in a Turkish door and furniture factory, and introductory-call process | Founder facts |
Frequently asked questions
Can I collect data for OEE without modifying the PLC?
Yes. FactoryVision counts visible finished parts and tracks downtime without wiring into the machine. A complete OEE calculation also needs production-time, ideal-cycle-time, and quality information.
Does FactoryVision calculate every OEE factor?
FactoryVision counts finished parts and tracks downtime. A complete OEE calculation also requires planned production time, ideal cycle time, and separately recorded good-part counts.
Where do the models run?
The models run on a small computer in the factory, not in our cloud.
How long does setup take?
The setup target is under an hour per station. Teaching a cycle takes ten parts.