FactoryVision

Free course, module 1: Count finished work

On this page
  1. Day 1: Decide what to count
  2. How to create a production shift record
  3. Count finished parts with a camera
  4. The five-day course
  5. Sources and claims
  6. Frequently asked questions
  7. Your first-day exercise

Day 1: Decide what to count

Choose one part and answer these questions with the people who work at the station:

  1. **Which part will you count?** For example, a completed door leaf, furniture panel, or machined metal part.
  2. **At what point is it finished for this count?** Choose a clear point after the operation you want to measure.
  3. **Which work order and shift does the count belong to?** Record both so the next shift can identify the work.

A part that has passed through one operation is not necessarily a finished product. Decide whether your count covers the output of a particular operation or the finished product, and use that definition consistently.

A count also does not establish whether a part has passed quality inspection. Record quality-approved quantities separately when your process requires them.

Start by agreeing on a clear counting definition.Choose the part, define where it counts as finished, then record its work order and shift.1Choose partDecide what to count2Set pointDefine completion3Log workLink order and shift
Start by agreeing on a clear counting definition.

How to create a production shift record

Start with a record that the team can review at handover:

FieldWhat to record
DateProduction date
ShiftShift responsible for the work
Machine or stationWhere the part was produced
Work orderThe relevant work order
PartProduct or part being counted
Finished countQuantity that passed the agreed counting point
NotesStops, adjustments, or other events relevant to the record

At handover, check for duplicate or missing entries and confirm that the count belongs to the correct work order.

Count finished parts with a camera

FactoryVision counts finished parts.

Choose a counting point where finished parts can be clearly identified.

FactoryVision fits countable, discrete parts. It counts finished parts and tracks downtime; it is not an ERP, MES, or SCADA system.

FactoryVision runs in a Turkish door and furniture factory.

The five-day course

DayFocus
1Define the finished-part counting point and record the count.
2Associate the count with the correct work order.
3Agree on what to pass to the next shift.
4Check records for duplicate, missing, or incorrect entries.
5Compare the finished count with the dispatch plan.
The course moves from defining a count to reviewing it against dispatch.The five-day course covers a counting point, work orders, shift handover, record checks and the dispatch plan.Five-day course12345DayCounting point · Work order · Shift handover · Record check · Dispatch plan
The course moves from defining a count to reviewing it against dispatch.

Sources and claims

ClaimSource
FactoryVision is a working product available for purchase and runs in a Turkish door and furniture factory.Founder facts and voice, 2026-11-13
Buying starts with an introductory call; the company’s machines and processes inform the setup. The founder provided the booking URL.Founder facts and voice, 2026-11-13
FactoryVision fits countable, discrete parts; it is not an ERP, MES, or SCADA system.Founder facts and voice, 2026-11-13
The course is planned as five daily modules.Supplied T14 topic brief; course structure, not a measured product claim

Frequently asked questions

What does FactoryVision do?

FactoryVision counts finished parts and tracks downtime. It is not an ERP, MES, or SCADA system.

What types of parts does FactoryVision support?

FactoryVision fits countable, discrete parts. Continuous processes are outside its scope.

Where does FactoryVision currently run?

FactoryVision runs in a Turkish door and furniture factory.

How do we get started with FactoryVision?

Buying starts with an introductory call booked at https://calendly.com/esat-factoryvision/intro. After the call, we learn about your company, machines, and processes so the setup fits your operation.

Does a production count replace quality inspection?

No. A count records output at the agreed counting point and does not establish whether a part has passed quality inspection. Record quality-approved quantities separately when your process requires them.

Your first-day exercise

Choose one machine or station and one part. Write down the point at which that part is counted, then create a record with the date, shift, station, work order, and finished count. Review the definition with the people handing work between shifts. To discuss FactoryVision for your factory, book an introductory call. After the call, we learn about your company, machines, and processes so the setup fits your operation.