Daily Production Target Calculator for One Station

On this page
  1. Calculate a daily production target
  2. Spreadsheet template
  3. Record the shift result
  4. Track the target with FactoryVision
  5. Sources and claims
  6. Frequently asked questions
  7. Start with an introductory call

Calculate a daily production target

Calculation steps and the order check.Target calculation: subtract planned non-production time, divide by cycle time, apply the good-part rate, then compare with the order.1Net timeShift −non-production2CyclesNet time ÷ cycle3Good estimateCycles × good rate4OrderCompare estimate
Calculation steps and the order check.

FactoryVision counts visible finished parts against the station’s daily target and shows whether the station is on track, at risk or behind.

Gather these inputs for the station:

  • **Planned shift time:** The scheduled shift duration.
  • **Planned non-production time:** Scheduled periods when the station will not produce, including applicable breaks, maintenance and changeovers.
  • **Planned cycle time:** The time needed to complete one part. Record what the cycle time includes so the same time is not deducted twice.
  • **Expected good-part rate:** The share of completed parts expected to pass quality checks.
  • **Required good parts:** The quantity needed for the order.

Enter shift time, planned non-production time and cycle time in the same unit. This calculation assumes one part per cycle and includes only the losses entered in the inputs. Unplanned downtime and other losses must be accounted for separately.

Net operating time = Planned shift time − Planned non-production time

Complete cycles = Round down (Net operating time ÷ Planned cycle time)

Estimated good parts = Round down (Complete cycles × Expected good-part rate)

Difference from order = Estimated good parts − Required good parts

A negative difference means the estimated output falls short of the order quantity. The estimate is a planning input; the production target should also reflect the order and the station’s actual conditions.

Example

These figures are hypothetical and do not describe a factory’s actual production.

InputExample
Planned shift time480 minutes
Planned non-production time60 minutes
Planned cycle time2 minutes per part
Expected good-part rate95%
Required good parts220

Net operating time = 480 − 60 = 420 minutes Complete cycles = 420 ÷ 2 = 210 Estimated good parts = Round down (210 × 0.95) = 199 Difference from order = 199 − 220 = −21 parts

The estimated output is **199 good parts**, which is **21 parts short** of the order quantity.

Spreadsheet template

Enter the headings in row 1 and the inputs in row 2. Format the good-part rate as a percentage.

CellFieldInput or formula
A2Planned shift time, minutesEnter a number
B2Planned non-production time, minutesEnter a number
C2Planned cycle time, minutes per partEnter a number
D2Expected good-part rateEnter a percentage, such as `95%`
E2Required good partsEnter a whole number
F2Net operating time, minutes`=A2-B2`
G2Complete cycles`=INT(F2/C2)`
H2Estimated good parts`=INT(G2*D2)`
I2Difference from order`=H2-E2`

Before calculating, check that:

  • Shift time and required quantity are non-negative.
  • Planned non-production time is non-negative and does not exceed shift time.
  • Cycle time is greater than zero.
  • The good-part rate is between 0% and 100%.
  • Required good parts is a whole number.

For a daily target covering more than one shift, enter the total planned shift time and total planned non-production time for the period, provided the same cycle time and good-part rate apply.

Record the shift result

Inputs and their role in the calculation.Target inputs: shift and planned non-production time set net time; cycle time and good rate produce the estimate.InputUsed toShift timenet timeNon-productionsubtractCycle timedivideGood ratemultiplyOrdercompare
Inputs and their role in the calculation.

Use a separate row for each station and shift. Compare actual good parts with the target, and record downtime alongside the result.

DateStationShiftWork orderGood-part targetActual good partsActual minus targetDowntime, minutesDowntime reason / notes

The calculator estimates good output using an expected good-part rate. Record the **actual good-part count** after the applicable quality check; a count of finished parts alone does not establish how many passed inspection.

Track the target with FactoryVision

FactoryVision counts visible finished parts with one camera per machine, without additional machine sensors or wiring into the machine. It shows one status light per station:

  • **Green:** on track.
  • **Yellow:** at risk.
  • **Red:** behind.

Teaching a cycle takes 10 parts. The setup target is under one hour per station. The models run on a small computer inside the factory, not in FactoryVision’s cloud.

FactoryVision fits countable, discrete parts that the camera can see. It is not an ERP, MES or SCADA system. FactoryVision runs in a Turkish door and furniture factory.

FactoryVision compares finished-part counts with the day’s target. Use the same basis for both: the calculator estimates good parts, and a count of finished parts alone does not establish how many passed inspection. See the station light and the andon reading guide.

Sources and claims

ClaimSource
Calculation method, rounding, input checks and hypothetical exampleAuthor-proposed planning model
One camera per machine; finished-part counting; station status lights and their meaningsSupplied house-style sample, 2026-11-13
No additional machine sensors or wiring; local processing; 10 parts to teach a cycle; setup target under one hour per stationSupplied house-style sample, 2026-11-13
Scope for visible, countable discrete parts; not ERP, MES or SCADASupplied founder facts and house-style sample, 2026-11-13
Product runs in a Turkish door and furniture factory; introductory-call process and linkSupplied founder facts, 2026-11-13

Frequently asked questions

How does the daily target calculation account for scrap and quality defects?

The calculation multiplies complete cycles by the expected good-part rate and rounds down to estimate good parts. Actual good parts are verified and recorded after inspection.

What does a negative difference from the order mean?

A negative difference means the estimated output falls short of the required order quantity under the planned shift time and cycle time. The shortfall must be addressed before finalizing the daily target.

Does FactoryVision require machine sensors or wiring?

No. FactoryVision counts visible finished parts using one camera per machine, without additional machine sensors or wiring into the machine.

Which manufacturing processes and parts does FactoryVision support?

FactoryVision fits countable, discrete parts that the camera can see. It is not an ERP, MES or SCADA system. It runs in a Turkish door and furniture factory.

How does a factory get started with FactoryVision?

Buying starts with an introductory call booked at https://calendly.com/esat-factoryvision/intro. After the call, setup is planned to fit the factory's machines and processes.

Start with an introductory call

Buying FactoryVision begins with an introductory call. After the call, we get to know your company so the setup fits your machines and processes. Book an introductory call

Request an intro call